Monthly Report of the Superintendent of Construction

Report for June, 1865

No copy made

Summary

Work has progressed favorably.

Kinsley and Clarkson have been prompt and ? and finished the essential parts of brickwork.

C. Edmonson has put on the frame of the roof and is engaged in covering it in preparatory to receiving the slate and tin covering.

George H. Plant has delivered during the month about 90,000 brick.

Nicholas Acker has delivered 64 barrels of lime, 10 barrels of cement and 200 loads of sand.

J.R. Elvans has furnished all the nails, ironwork and hardware.

(Report includes a list of bills for the above work certified and paid.)