Monthly Report of the Superintendent of Construction

Report for September, 1865

No copy made

Report for September 1865 from A.B. Young to Dr. J.P. Horowitz

Summary

Almost all brickwork is done (all of which can be done at present is completed).

The entire plastering (except the white coat of the basement story) is finished.

Plumbers, gas fitters, carpenters all at work.

The materials from the old building reserved from public sale have all been worked into the new building, taking the place of new materials.

(See copies)